Construction of a small hydropower plant of maximum 10 MW
Client
A company operating in the energy sector.
Development plans
The company plans to increase the production capacity of energy from renewable sources. This objective will be achieved by the establishment of a new hydropower plant. The location of the project allows it to utilize local hydropower resources.
Project
The project involves the construction of a small hydropower plant of 9 MW. The project’s total value was estimated at PLN 14 million, including eligible costs of PLN 11 million.
Benefits
Acquisition of an EU grant of PLN 2.2 million (20% of eligible costs) will enable the introduction of green energy to the market and diversification of energy resources and will therfore meet the requirements of the country’s energy policy.
You might also be interested in:
Our services