Construction of a small hydropower plant of maximum 10 MW

Client

A company operating in the energy sector.

Development plans

The company plans to increase the production capacity of energy from renewable sources. This objective will be achieved by the establishment of a new hydropower plant. The location of the project allows it to utilize local hydropower resources.

Project

The project involves the construction of a small hydropower plant of 9 MW. The project’s total value was estimated at PLN 14 million, including eligible costs of PLN 11 million.

Benefits

Acquisition of an EU grant of PLN 2.2 million (20% of eligible costs) will enable the introduction of green energy to the market and diversification of energy resources and will therfore meet the requirements of the country’s energy policy.   

 

 